September 21, 2018Experience start
-
September 11, 2018Students forming teams and evaluation request for proposals
-
September 18, 2018Project proposals sent to companies
-
September 25, 2018Initial meeting with company / develop project expectations / project plan agreed on
-
November 6, 2018Check point
-
November 27, 2018Report due / company presentation
-
December 1, 2018Experience end
Timeline
-
September 21, 2018Experience start
-
September 11, 2018Students forming teams and evaluation request for proposals
Students will form teams of 5 people and evaluate request for proposals by companies. Students will then develop and submit proposals to companies.
-
September 18, 2018Project proposals sent to companies
Companies are expected to make selections this week.
-
September 25, 2018Initial meeting with company / develop project expectations / project plan agreed on
Students will meet with companies and develop project expectations/ project plans.
-
November 6, 2018Check point
Instructor meets with teams to learn of progress.
-
November 27, 2018Report due / company presentation
Reports are sent to companies and private presentation to the company.
-
December 4, 2018Company feedback to students
Companies will provide verbal and/or written feedback to students presentations and project report.
-
December 1, 2018Experience end
Experience scope
Categories
Information technologySkills
competitive analysis change management it consultancy process analysis business strategyStudent-consultants will develop a plan and strategic solution for your organizational challenge or objective surrounding Information Technology or Information Services.
Students
Final project deliverables include:
- A 30-page comprehensive report.
- A 20-minute presentation, followed by Q&A.
Project timeline
-
September 21, 2018Experience start
-
September 11, 2018Students forming teams and evaluation request for proposals
-
September 18, 2018Project proposals sent to companies
-
September 25, 2018Initial meeting with company / develop project expectations / project plan agreed on
-
November 6, 2018Check point
-
November 27, 2018Report due / company presentation
-
December 1, 2018Experience end
Timeline
-
September 21, 2018Experience start
-
September 11, 2018Students forming teams and evaluation request for proposals
Students will form teams of 5 people and evaluate request for proposals by companies. Students will then develop and submit proposals to companies.
-
September 18, 2018Project proposals sent to companies
Companies are expected to make selections this week.
-
September 25, 2018Initial meeting with company / develop project expectations / project plan agreed on
Students will meet with companies and develop project expectations/ project plans.
-
November 6, 2018Check point
Instructor meets with teams to learn of progress.
-
November 27, 2018Report due / company presentation
Reports are sent to companies and private presentation to the company.
-
December 4, 2018Company feedback to students
Companies will provide verbal and/or written feedback to students presentations and project report.
-
December 1, 2018Experience end
Project Examples
Requirements
Starting this September, a team of 5 Business/IT students will dedicate 125+ hours over the full semester developing and/or implementing a custom IT plan, recommendations, and strategic solutions for your organization.
Based on your challenge or opportunity, the student-consultant group(s) will provide detailed insights that can assist your organization in overcoming IT obstacles and becoming more competitive and effective overall.
Project examples include, but are not limited to:
- Strategic use of information technology: Facilitating the execution of your business strategy through creative and strategic deployment of an existing IT program.
- Using information technology as a strategic weapon: Identifying and creating a sustainable competitive advantage through information technology.
- Managing security and risks: Identifying IT system risks and preventative measures.
- IT management analysis: Identifying who determines the IT strategy in your organization and how effective your IT governance is, including developing recommendations for improvement.
- Using IT to improve organizational effectiveness: Identifying areas of opportunity for efficiency/ productivity and the most effective and comprehensive IT solutions.
- Managing competitive landscape changes: Identifying and implementing relevant IT systems in anticipation of or in response to industry changes.
Additional company criteria
Companies must answer the following questions to submit a match request to this experience:
Additional company criteria
Companies must answer the following questions to submit a match request to this experience:
Timeline
-
September 21, 2018Experience start
-
September 11, 2018Students forming teams and evaluation request for proposals
-
September 18, 2018Project proposals sent to companies
-
September 25, 2018Initial meeting with company / develop project expectations / project plan agreed on
-
November 6, 2018Check point
-
November 27, 2018Report due / company presentation
-
December 1, 2018Experience end
Timeline
-
September 21, 2018Experience start
-
September 11, 2018Students forming teams and evaluation request for proposals
Students will form teams of 5 people and evaluate request for proposals by companies. Students will then develop and submit proposals to companies.
-
September 18, 2018Project proposals sent to companies
Companies are expected to make selections this week.
-
September 25, 2018Initial meeting with company / develop project expectations / project plan agreed on
Students will meet with companies and develop project expectations/ project plans.
-
November 6, 2018Check point
Instructor meets with teams to learn of progress.
-
November 27, 2018Report due / company presentation
Reports are sent to companies and private presentation to the company.
-
December 4, 2018Company feedback to students
Companies will provide verbal and/or written feedback to students presentations and project report.
-
December 1, 2018Experience end